Green Gabions Mesh

Material Delivery 
Green gabions mesh
are supplied in the collapsed form, folded and bundled. The bundles are compressed, strapped together and wrapped with plastic at the factory for easy shipping and handling. Each bundle is labelled with a tag reporting the sizes of the units contained. Lacing wire is supplied in coils. Ring fasteners (Figure 4) are shipped inboxes which must be stored in a dry environment.

Assembly 
The folded units shall be taken out from the bundle and placed on a hard flat surface. Green Gabion Baskets Mesh units shall be opened, unfolded and pressed out to their original shape. When the units are unfolded for assembly, they will have one or two shipping folds. They can be removed by placing the fold over a board and walking along the sides.

Fixing Procedure 
When using lacing wire, cut off a piece of wire approximately 1,5 times the length of the edge to be tied. The maximum length of the edge to be tied at one time shall not exceed 1 m. Longer edges shall be joined by several lengths of wire. Lacing wires shall be secured around the selvedge wire or heavier edge wire, where present, by looping and twisting the lacing wire around itself. Proceed tying with alternate double and single loops (Figure 3). Double loops shall be made at intervals not greater than 300 mm. All panels shall be pulled tightly together during the tying

operation. Pliers (Figure 5) may be used to create tight joints. The other end of the lacing wire shall be secured by again looping and twisting the wire around itself. When using lacing wire to assemble the units care should be taken to avoid damaging the wire coating. When steel ring fasteners are used, the custom made Yihang Manual Spenax Tool (Figure 5) is required and available for hire. Rings shall be installed at the top and the bottom connections of the end and centre diaphragms and then a maximum spacing of 100 mm along all edges shall be used.Connect with ring fasteners between adjacent units.Connections made along the panel edges assure a flat surface for fill placement.     

Foundation Preparation 
The foundation on which the Green Gabion Baskets Mesh units are to be placed shall be level and graded to the elevations as shown on the project construction drawings, and free of surface irregularities, loose material and vegetation inaccordance with the project specifications.